Location
Alpharetta, GA
Vertical AVTV installed AV systems throughout the first floor of Delta Dental's new office building in Alpharetta, Georgia. Vertical addressed the client's need for a large and divisible training space equipped for multiple uses and configurations (trainings/classes, video conferencing calls, company-wide meetings). Digital signage displays and players were provided to offer nationwide rollout of company communications.
Duration & Date Completed
Commenced April 2020 and completed August 2020

Room Types Installed
Huddle, Training, Conference Center, Pre-Function Spaces, Break Room/Lounge

Scope
Design, engineering, installation, and ongoing support of client's AV and digital signage systems

Challenges and Outcome
Supply chain issues due to COVID-19 caused delays with installation of hardware. The presence of multiple vendors onsite at once (general contractors, electricians, painters, interior designers, etc.) required thoughful scheduling with all parties involved. Vertical worked with the GC and the client's facilities teams to coordinate schedules.